Tuesday, June 30, 2015

Prefabricated exterior panels installation - Day 2

Andrew & Joey joined Rane & Jan for another day of hard work.  All the wall panels had to be installed in preparation for the roof panels arriving on Thursday.


2nd batch of panels ready to be lifted up & secured in place

Andrew securing one of the wall panels

By the end of Day 2



Monday, June 29, 2015

Prefabricated exterior panels installation - Day 1

Collective Carpentry has been working hard prefabricating the panels in their Invermere factory over the past few weeks.  Prior to that, lots of planning happened between Brett, Alison & Rane/Jan.

The panels finally arrived yesterday evening.  This morning, Rane and Jan (pro: Yan) were ready to install the first batch of panels.  What an exciting day!

They came prepared!

Before

The crane & the panels meet for the first time

The first piece

Jan & Rane securing the main floor panels

After

By lunch time



Saturday, June 6, 2015

The concrete slab

Bitumen waterproofing (black in color)


Rebars in place


Pouring concrete to form the slab on 5 June 2015

While all these were happening, the house was being built in Invermere by Collective Carpentry.